Project Category:
Status:
Project Scope
The Project scope included five separate components as follows:
Part 1: Institutional Development Component- FHA Component Part2: Provincial Highway Component (212 km, assuming 3 or 4 contract packages)- FHA
Part3: National Highway Authority Component (210 km, assuming 4 or 5 contract packages)
Part 4: Rural Access Roads-Package A (Design 290 km, Review 60 km,
Supervision 350 km)-W&S Department
Part5: Rural Access Road-Package B (Design 310 km, Review 40 km, Supervision 350 km)-W&S Department

Name of Client:
- Asian Development Bank (ABD)/Highway Authority (FHA) KPK Pakistan
Project Duration/ Timeline:
December 2005 to May 2010
Approx. value of the contract:
US$ 289,337
Location:
- Khyber Pakhtunkhwa